WBJECA | Computer | 2025A risk in a software project has a probability of occurrence of 0.3 and the potential loss if it occurs is estimated to be Rs. 2,00,000. What is the Risk Exposure (RE) for this risk?

A risk in a software project has a probability of occurrence of 0.3 and the potential loss if it occurs is estimated to be Rs. 2,00,000. What is the Risk Exposure (RE) for this risk?